Air Cannons Eliminate Blockages Caused By Sticky Iron Ore
Products Used Hurricane Air Cannon
Product Types Used Air Cannon Solutions , Air Cannons
Solutions Installation
Industry Cement
Customer TXI Hunter Cement, New Braunfels, TX

Problem

TXI runs 100 tons per month of iron ore into the clinker feed from one line.

TXI Cement is the largest producer of cement in Texas and a major cement producer in California. TXI is also a major supplier of construction aggregate, ready-mix concrete and concrete products. At their New Braunfels, TX plant they run 100 tons per month of iron ore into the clinker feed from one line.

When the iron ore would come in wet, or it would rain, the iron ore got very sticky, and would stick to the inside of the silo. TXI would shut down for regular 24 hour periods so they could manually air lance the resulting blockage that was causing low feed rates.

Solution

After installing the air cannons, TXI was able to continue working without stopping production.

Working with Martin Engineering, they developed a plan to install a series of air cannons in an ascending spiral on the cone section of the silo, keeping the material flowing at a constant feed rate. With the powerful discharge from the reservoir of compressed air, the Martin® Hurricane Air Cannons successfully removed the material from the silo walls.

Martin® Hurricane Air Cannons were designed for simple maintenance. The complete valve assembly can be removed in one easy step, working from one side of the tank. The Martin® Hurricane Air Cannons also deliver the maximum discharge strength from high velocity output with less air volume, for a highly effective discharge and reduced operating costs. The four air cannons, including blow pipes, air lines and control systems were installed by a MartinPLUS® Service Team.

Results

The Martin® Hurricane Air Cannon improves the flow of materials and prevents outages due to blockages.

The air cannons eliminated the blockages. The timed discharge of the air cannons has successfully prevented the accumulation that impacted the process efficiency and required frequent interruptions for manual clean out. Since the installation, TXI has not had to stop production, saving time and money. “The air cannons have been a success,” declared Sudhanva Bhat, Maintenance Manager at the plant.

Resources

PDF - Printable Version of Case Study Download
Brochure - Air Cannons Download
Brochure - MartinPLUS® Services Download
Brochure - Martin Engineering Corporate Profile Download

View Additional Resources

We've solved your problem somewhere before!

While your problem seems unique and frustrating, with 70+ years of solving similar problems around the world, and with the most experienced and educated people on our teams, we can assure you that we’ve “Been There, Done That.” At least close enough to know what needs to be done next and adjust for your situation.

Put Us To The Test For Free! Let Us Give You a Solution.